Stage 1 - Ashmore construction commences

posted 19 Jun 2013, 03:42 by Friends of Erskineville   [ updated 19 Jun 2013, 03:44 ]

Construction of stage one is planned to commence 24th June 2013.

The construction is being undertaken by Richard Crookes Constructions, and is anticipated to take approximately 18 months. Key activities and the approximate duration of each during this time are outlined below:

ActivityDetailDuration
Site establishmentSet up of crane/s, scaffolding, site hoarding and site office.2 months
EarthworksExcavation of bulk material for export from the site and concrete piling along the perimeter of the building and of footings.3 months
ConstructionConstruction of buildings.13 months

A temporary site office and staff compound will also be set up in the north of the site, and the existing display suite will be retained.

The hours of work on site, in accordance with those approved by the City of Sydney, are:

  • Monday to Friday: 7:30am – 5:30pm
  • Saturday: 7:30am – 3:30pm
  • Sunday: No work.